The NIF facility convenes a Facility Advisory and Scheduling Committee (FASC) meeting annually, usually in mid-May, to approve the baseline schedule for the following government fiscal year. The schedule that is discussed and approved has been developed in the preceding six weeks through a series of dedicated meetings with stakeholders. DLI shots will be paired with NSA main-chamber experiments during that six-week period (April to early May) after the main-chamber experiments have been tentatively scheduled. If a dedicated DLI shot date was awarded, the date would be directly scheduled in the scheduled building process. Once the schedule is approved by the FASC, changes are managed through formal, software-based schedule change requests (SCRs). Changes to the DLI experiment riding along on the main-chamber shot will be managed through the SCR tool.